Eloy WWTP Expansion
| Project Owner: City of Eloy |
Date: July 1999 |
Location: Eloy |
![]() |
![]() |
Project Description
This WWTP project upgraded the existing facility by replacing the settling ponds with a Parkson Biolac system Called a Type-R Wave OX. The settling ponds were reconfigured to accommodate Parkson’s system with the addition of concrete dividing walls and pond liners. In addition to the new treatment system, a new lift station headworks facility was added that included elevated bar screens, a screw conveyor, and a new 24” main transmission line from the headworks to the Biolac system.